How can priorities be set in deciding the levels of monitoring?

 Priorities can be set up in deciding the levels of monitoring in the following ways:-

Critical Path activities

Any delay in an activity on the critical path will cause a delay in the completion date for the project. Critical path activities are likely to have a very high priority for close monitoring.

Activities with no free float  

A delay in any activity with no free float will delay at least some subsequent activities even though if the delay is less than the trial float, it might not delay the project completion date. Free float is the amount of time an activity may be delayed without affecting any subsequent activity.

High-risk activities

A set of high-risk activities should be identified as part of the initial risk profiling exercise. If we are using the PERT three-estimate approach we will designate as high-risk activities duration varianceThese activities will be given close attention because they are most likely to overrun or overspend.

Activities using critical resources

Activities can be critical because they are very expensive in the case of a specialized contract programmer. Staff or other resources might be available only for an unlimited period, especially if they are controlled outside the project team. In any event, an activity that demands critical resources requires a high level of monitoring.


Comments

Popular posts from this blog

Suppose that a data warehouse for Big-University consists of the following four dimensions: student, course, semester, and instructor, and two measures count and avg_grade. When at the lowest conceptual level (e.g., for a given student, course, semester, and instructor combination), the avg_grade measure stores the actual course grade of the student. At higher conceptual levels, avg_grade stores the average grade for the given combination. a) Draw a snowflake schema diagram for the data warehouse. b) Starting with the base cuboid [student, course, semester, instructor], what specific OLAP operations (e.g., roll-up from semester to year) should one perform in order to list the average grade of CS courses for each BigUniversity student. c) If each dimension has five levels (including all), such as “student < major < status < university < all”, how many cuboids will this cube contain (including the base and apex cuboids)?

Suppose that a data warehouse consists of the four dimensions; date, spectator, location, and game, and the two measures, count and charge, where charge is the fee that a spectator pays when watching a game on a given date. Spectators may be students, adults, or seniors, with each category having its own charge rate. a) Draw a star schema diagram for the data b) Starting with the base cuboid [date; spectator; location; game], what specific OLAP operations should perform in order to list the total charge paid by student spectators at GM Place in 2004?

Discuss classification or taxonomy of virtualization at different levels.